If you are a subcontractor or supplier owed money on a Florida job, several dates can start running at once. This guide covers Florida construction lien deadlines for a subcontractor who is owed money, step by step. The exact dates depend on the facts of each project, so use these steps to organize your records. This page is written by Eduardo A. Maura of Ayala Law PA. The firm handles construction litigation for businesses in Tampa, Hillsborough County and the wider Tampa Bay area.
What Chapter 713 Covers for Subcontractors and Suppliers
Chapter 713 is Florida’s construction lien law.
A contract claim is a different tool. Florida courts state the elements of breach of contract as a valid contract, a material breach, and damages (Grove Isle Ass’n v. Grove Isle Assocs., LLLP). Each one has its own timing, so don’t treat one date as the other’s.
Fees are a separate question. Under Florida law, each party generally pays its own attorney’s fees unless a contract or statute provides otherwise (Price v. Tyler). Read your subcontract before you assume fees can be recovered.
These rules apply on jobs in Brandon, Riverview, Plant City and Temple Terrace, just as they do in Tampa.

Not sure what your next step is?
Talk it through with our team — we can walk you through how a situation like yours is usually handled and what your options are.
Lien Timing for Labor and Materials Furnished
Florida’s general accrual rule says a cause of action accrues when its last element occurs (Fla. Stat. § 95.031). Your records need to prove the dates tied to your furnishing.
Substantive work counts. Small pre-work, like a site visit or a price quote, is often argued about.
Build the record as you go. Keep daily logs, timesheets, delivery tickets and signed change orders. Each one shows a date and what you supplied. Owners and contractors often dispute which day counts, so a clear paper trail helps you answer that fight.
The Notice to Owner Is an Early Step
Chapter 713 includes a notice to owner step for many claimants, and it comes early in the job. Put it on your calendar from the first day you supply materials or labor.
A clear notice names you, the owner, the project, and the amount you say is unpaid. Vague notices invite arguments. Keep the signed copy, the delivery method, and the date it went out.
Proof of service matters. If the owner says it never got the notice, your records are your answer. Save the certified mail receipt, the courier tracking, or the email with delivery confirmation.
That’s why the notice belongs in the same file as your first-day records.
The Claim of Lien Deadline After Your Last Day
That clock ties to your final work, so your last furnishing date deserves the most care.
Don’t assume the last invoice date is the last work date. Lay out the sequence: last delivery, last crew day, last approved change order. Then match each entry to a document.
A disagreement over the last date can change which deadline applies. Settle the record early, while people still remember the job.
Missing this deadline can cost you the lien, even when the balance is still owed. That is the core risk in this step.
Have questions about what happened?
Ask our team directly. Tell us what you are dealing with and we will explain how the process works from here.
Enforcing the Lien and the Lawsuit Deadlines
Recording a lien is not the same as enforcing it. Enforcing a lien can involve a lawsuit to foreclose it.
Section 95.11(3)(b) of the Florida Statutes applies to actions founded on the design, planning, or construction of an improvement to real property. Under the four-year provision of Fla. Stat. § 95.11, an action founded on the design, planning, or construction of an improvement to real property runs from the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of occupancy, or a certificate of completion, or the date of abandonment of construction if not completed, whichever date is earliest. The first is the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of occupancy, or a certificate of completion. The second is the date construction is abandoned, if it was not completed. The clock does not simply start on the day work physically ended. When the claim involves a latent defect, the time instead runs from when the defect is discovered or should have been discovered with the exercise of due diligence. For a newly constructed single-dwelling residential building used as a model home, the time begins on the date a deed is recorded first transferring title to another party. In any event, the action must be commenced within 7 years after the earliest of those same dates: the issuance of a temporary certificate of occupancy, certificate of occupancy, or certificate of completion, or the abandonment of construction if not completed. One exception applies to claims that arise out of the conduct, transaction, or occurrence set out, or attempted to be set out, in a pleading. Counterclaims, cross-claims, and third-party claims of that kind may be commenced up to 1 year after that pleading is served, even if they would otherwise be time barred. If the project involves multiple buildings, each building is considered its own improvement for purposes of determining the limitations period.
Payment bonds have their own rule. For a claim on a payment bond where the principal is a contractor, subcontractor, or sub-subcontractor, the time runs from the last furnishing of labor, services, or materials, or from the contractor’s last furnishing on the same project if the contractor is the principal on a bond on that project, whichever is later, except for actions governed by s. 255.05(10), s. 337.18(1), or s. 713.23(1)(e) (Fla. Stat. § 95.11). For an action to enforce a payment bond claim on a construction project, the time runs from the last furnishing of labor, services, or materials, or from the contractor’s last furnishing on the same project if the contractor is the principal on a bond on that project, whichever is later, with listed exceptions.
Final Payment Records Show What Is Still Owed
Your pay applications, retainage records and final payment requests usually show what remains unpaid. Keep them in the same file as your lien dates.
Compare your lien amount to your invoices. A mismatch gives an owner an easy argument. Use the same numbers in every document.
Ask for payment status in writing and save the reply.
Filing a Claim of Lien: What the Document Should Include
A claim of lien should match your records. Errors in those dates create disputes.
Use the same dates and figures as your notice to owner and your invoices. Consistency makes your claim easier to follow.
After recording, keep the recorded copy, the recording information, and the proof you served the owner. Together, these show what you filed and when.
Don’t guess at numbers. If the amount is uncertain, sort it out before you file.

Why Missing a Deadline Can End a Lien Claim
A missed lien deadline can leave you with only the contract claim. That claim has its own elements and fee rules, so it is a different case.
Winning a judgment is one step. Collecting it is another. A judgment becomes a lien on real property in a county when a certified copy is recorded there with the required address. Under Fla. Stat. § 55.10, that lien runs for an initial 10 years for recordings made on or after July 1, 1994.
Can a missed lien deadline end the debt?
A missed lien deadline can end the lien. The contract claim may still exist, and it has its own time limits.
Who pays attorney’s fees in these cases?
Under Florida law, each party generally pays its own fees unless a contract or statute says otherwise. Check your subcontract first.
When should a subcontractor get help?
Reach out as soon as a payment is in dispute, because several dates may already be running. For broader construction disputes, see the firm’s construction litigation practice.
If an unpaid invoice on a Tampa-area project has you tracking these dates, contact Ayala Law PA at (813) 414-5715 or through the contact page to talk through your timeline. The firm handles construction litigation, including lien foreclosure.