Your contract was signed, the work was done or the goods were delivered, and then the other side stopped paying or performing. Now you need to know what you can do next.
Contract disputes often turn on what the agreement actually says and whether each party did what it required. The harmed party may be able to recover money for the loss. The right path depends on the contract and the facts.
What a Breach of Contract Claim Is and Who It Is For
Most of these disputes turn on four questions: was there a valid agreement, did you perform or were you ready to perform, did the other side fail to perform, and did that failure cause a loss?
Tampa businesses see these disputes in many forms. A general contractor may not be paid in full. A subcontractor or supplier may wait months for money owed for labor or materials. Developers, property owners and commercial companies also sign agreements that can fall apart.
Ayala Law PA focuses on business and commercial litigation, and contract disputes are part of that work. For a wider overview, read our Florida contract disputes guide.
Not sure what your next step is?
Talk it through with our team — we can walk you through how a situation like yours is usually handled and what your options are.
Construction and Commercial Contract Disputes We Handle
Construction and commercial contract breaches usually involve money, scope, timing or the quality of the work. Common examples include:
- Unpaid or late payments to subcontractors, suppliers or general contractors
- Unpaid change orders and disagreements over the agreed scope
- Missed deadlines, defective or incomplete work, and wrongful termination
- Construction contract fraud or misrepresentation tied to a signed agreement
- Lien foreclosure as part of a payment dispute on a construction project
- Supply, vendor, distribution and service agreements between businesses
- Real estate contract disputes that are litigation matters, not routine closings
Each category has its own proof and its own deadlines. The contract language and the payment records usually shape where a case starts.
What a Business Can Recover After a Breach
The amount depends on the contract terms, the proof and the losses involved.
- Direct damages: a category of loss a party may describe in a dispute.
- Consequential damages: a category of loss a party may describe in a dispute, such as lost profit.
- Equitable relief: a category of remedy a party may seek in a dispute, such as a request for a court order.
- Attorney fees: In any action to enforce a lien, including a lien transferred to security, or to enforce a claim against a bond, Florida’s lien enforcement statute entitles the prevailing party to recover a reasonable attorney’s fee for trial and appeal or for arbitration, in an amount set by the court. If a contract lets one party recover attorney’s fees for enforcing it, a court may also allow reasonable fees to the other party when that party prevails, as plaintiff or defendant, for contracts entered into on or after October 1, 1988, under § 57.105.
A party that announces it will not perform creates a special issue. No one can promise a particular amount, because the documents and contract terms decide much of the outcome.
How a Breach of Contract Dispute Moves Forward
Most disputes start with a file review and a written demand, then move toward negotiation, mediation, arbitration or a lawsuit. The order depends on what your contract says.
- Review. We look at the contract, change orders, invoices, payment history and correspondence to find the breach and the amount at stake.
- Notice. A written demand names the breach and the contract clause. Check whether the contract requires notice and a chance to fix the problem. Courts generally do not treat a notice step as a condition unless the words clearly require it, as Covelli Family explains.
- Mediation or negotiation. On one party’s request, provided that party is willing and able to pay the mediation costs or the costs can be equitably divided between the parties, a Florida court must refer most civil damages cases to mediation, unless a listed exception applies, under the court mediation statute. One exception is an agreement to binding arbitration.
- Arbitration. A written arbitration agreement is enforceable under Florida’s arbitration statute, except on a ground that exists at law or in equity for the revocation of a contract. Federal law can also apply to contracts involving interstate commerce, under 9 U.S.C. § 2.
- Lawsuit. If arbitration does not apply, the case is filed in the proper Florida court. For many Tampa-area projects, that is Hillsborough County. Discovery, motions, trial or settlement follow.
Timing varies with the court calendar, the complexity of the claims and whether the parties settle. No timeline is fixed.
Deadlines and Records to Gather Before You Call
Deadlines can run before a dispute feels urgent, so note the key dates first. Florida sets different time limits for different claims.
- Written contracts: generally five years, under Fla. Stat. § 95.11.
- Specific performance (a court order to perform).
- Lien recording: a claim of lien may be recorded no later than 90 days after the last labor, services or materials were furnished, and if the direct contract is terminated before completion, a claim attaching before termination may not be recorded after 90 days following the termination or after final furnishing, whichever occurs first, under § 713.08.
- Lien enforcement: Fla. Stat. § 713.22 reads: “(1) A lien provided by this part does not continue for a longer period than 1 year after the claim of lien has been recorded or 1 year after the recording of an amended claim of lien that shows a later date of final furnishing of labor, services, or materials, unless within that time an action to enforce the lien is commenced in a court of competent jurisdiction.”
- Construction defect claims: written notice of claim must be served at least 60 days before filing suit, or at least 120 days before filing an action involving an association representing more than 20 parcels, under § 558.004.
Gather these records:
- The signed contract and any amendments
- Purchase orders, change orders and daily logs
- Invoices, lien notices and payment records
- Emails and texts about the work or payments
Also check the contractor’s license. Under § 489.128, a contract with an unlicensed contractor can be unenforceable by that contractor.
Why Work With Ayala Law PA on a Tampa Contract Dispute
Ayala Law PA is located at 1646 W Snow Ave, Tampa, FL 33606. The firm serves Tampa, Hillsborough County, Brandon, Riverview, Plant City, Temple Terrace and the Tampa Bay area from that Tampa office.
Eduardo A. Maura is the responsible lawyer for this page. Our lawyers and support staff work together on business and construction disputes.
The firm focuses on business litigation, commercial litigation, contract disputes, shareholder disputes, construction litigation, real estate litigation and international trade litigation. That work takes place in Florida courts and arbitration.
Not sure what your next step is?
Talk it through with our team — we can walk you through how a situation like yours is usually handled and what your options are.
Common Questions About Breach of Contract Help in Tampa
Here are direct answers to common questions about breach of contract disputes in Tampa.
How much do contract lawyers cost?
Fees depend on the complexity of the dispute and the fee arrangement, which we discuss with you directly. Ayala Law PA does not offer a free consultation.
What kind of lawyer do I need to sue a contractor in Florida?
You need a litigation lawyer who handles construction and contract disputes. Our business and construction litigation work covers this type of claim.
Are construction attorneys worth it?
The value depends on the amount in dispute, the contract terms and the deadlines involved. No result can be promised.
Can a dispute be resolved without a lawsuit?
Negotiation and mediation can resolve a dispute before a lawsuit is filed. Your contract may also require arbitration instead of court.
Can I recover attorney fees?
Under § 57.105(1), the court shall award a reasonable attorney’s fee, including prejudgment interest, to be paid to the prevailing party in equal amounts by the losing party and the losing party’s attorney, on any claim or defense at any time during a civil proceeding in which the court finds that the losing party or its attorney knew or should have known that the claim or defense, when first presented or at any time before trial, was not supported by the material facts necessary to establish it or would not be supported by then-existing law applied to those material facts. Under § 57.105(3)(a), monetary sanctions may not be awarded under paragraph (1)(b) if the court determines that the claim or defense was initially presented to the court as a good faith argument for the extension, modification, or reversal of existing law or the establishment of new law, as it applied to the material facts, with a reasonable expectation of success. Separately, under § 57.105(7), if a contract entered into on or after October 1, 1988 allows attorney’s fees to a party that must take action to enforce it, the court may also allow reasonable attorney’s fees to the other party when that party prevails in any action, whether as plaintiff or defendant, with respect to the contract.
Next Step for a Tampa Contract Dispute
If a contractor halted work or a customer won’t pay under a signed agreement, the deadlines may already be running, so call (813) 414-5715 or request a case evaluation through our contact page and bring your contract and payment records.