How Long Do You Have to Sue Over Commercial Property in Florida?

Filing deadlines for commercial property disputes depend on the type of claim, the contract language, and the facts. Ayala Law PA focuses on commercial, contract, real estate and construction litigation for businesses in Tampa and across Hillsborough County.

By Eduardo A. Maura · Published October 24, 2026

The Short Answer: Why Florida Deadlines Are Rarely One Number

There is no single answer to how long to sue over commercial property Florida disputes allow. The deadline depends on the legal theory behind your claim, and the clock often starts on a date other than the day you signed or closed. Fla. Stat. § 95.11 sets general limits by category of claim, so the category matters.

Many owners and tenants assume they have years to act. That assumption can cost them. A written lease claim, an oral side deal, a construction defect, and a title problem can each carry a different time limit.

Start with the claim, not the calendar. First, name the type of claim. Second, find the start date that applies to that claim. Third, check for notice steps, pauses in the clock, or shorter contract terms that could change the math.

Shorter contract terms are not a safe shortcut. Under § 95.03, a contract provision that sets a filing period shorter than the statute is void.

Not sure what your next step is?

Talk it through with our team — we can walk you through how a situation like yours is usually handled and what your options are.

What Is a Statute of Limitations?

A statute of limitations is the time limit for filing a lawsuit after a claim arises. If you file after that limit, the court can dismiss the case, even when the underlying dispute has merit.

Florida ties the start of that clock to accrual. Under § 95.031, a cause of action accrues when the last element constituting the cause of action occurs. The clock does not always start when a deal is signed. It starts when the last element of the claim occurs, except as the statute otherwise provides in subsection (2), s. 95.051, or elsewhere in the statutes.

Some time limits work differently. Lawyers sometimes call an outer limit that runs no matter when harm was found a statute of repose. Florida’s construction rules include an outer limit of this kind, covered in the construction section below.

Knowing which kind of limit applies helps you avoid a common surprise. A deadline can expire before you realize the claim existed.

Florida’s Statute of Limitations: Know Your Deadlines

Florida’s general periods are set out in Fla. Stat. § 95.11. The statute groups claims by category and gives each one a time limit. The category your claim falls into decides how much time remains.

The periods vary widely. An action on a judgment or decree of a Florida court of record has a 20-year period under the statute. Many other claims have far shorter windows, so a claim that looks simple may sit in a category you did not expect.

For commercial property, four categories matter most: written contracts, oral contracts, construction claims, and real property possession. The sections below cover each one. These periods are general summaries, and the deadline that fits your specific claim controls.

Written Contracts and Commercial Leases — 5 Years

Lease and business property disputes can raise several different claims, and the timing of each depends on the facts of the matter.

Unpaid rent, unpaid charges, and other breaches of a written lease usually fall here. Under § 95.031, the time to begin an action under a statute of limitations runs from the time the cause of action accrues, and a cause of action accrues when the last element constituting it occurs. An older breach may expire while a newer one is still within time.

A written agreement also limits other theories. In Williams v. Johnson, the court held that where an express contract covers the same subject matter, claims arising from that relationship will not support a claim for unjust enrichment. Keep the lease, every notice, and every payment record together. For more on lease timing, see our commercial lease deadline guide.

Oral Contracts — 4 Years

That shorter period is the key difference from a written deal.

Time is only one problem. The Florida Supreme Court has held that an oral contract is still subject to the basic requirements of contract law. Those include offer, acceptance, consideration, and sufficient specification of essential terms, as explained in St. Joe Corp. v. McIver.

That last point is where many oral deals fail. If the essential terms were vague, a court may find that the basic elements are missing. Write down what you remember now, with names, dates, and amounts, while the facts are fresh.

A spacious industrial warehouse with stacked cardboard boxes for storage and shipping.

Real Property and Title Issues — 7 Years

Under Fla. Stat. § 95.12, a suit to recover real property or its possession cannot be maintained unless the person seeking recovery, or a predecessor or grantor, was in possession within seven years before the suit began.

Florida also recognizes adverse possession after seven years of continued possession under a claim of title. That doctrine has its own requirements under § 95.16.

Title disputes can turn on recording dates, competing claims, or who had possession and when. Owners should not assume a long period applies to a title problem just because they have held the property for years.

Not sure what your next step is?

Talk it through with our team — we can walk you through how a situation like yours is usually handled and what your options are.

Construction Claims, Notice Requirements, and Lien Deadlines

Under Florida law, an action founded on the design, planning, or construction of an improvement to real property generally must be commenced within four years, with the time running from the earliest of the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of occupancy, or a certificate of completion, or the date of abandonment of construction if not completed. When the action involves a latent defect, the time runs from when the defect is discovered or should have been discovered with the exercise of due diligence, but in any event the action must be commenced within seven years after that earliest date. For a latent defect, the time runs from when the defect is discovered or should have been discovered with the exercise of due diligence, and in any event the action must be commenced within 7 years after that earliest date. For most defects, the clock runs from the earliest certificate or abandonment date.

Those certificates include a temporary certificate of occupancy, a certificate of occupancy, or a certificate of completion. If construction is never finished, the abandonment date is the trigger.

Hidden defects follow a different rule. For a latent defect, time runs from when the defect was discovered or should have been discovered with due diligence. Even then, suit must be started within seven years after the earliest certificate or abandonment date.

Repairing completed work does not reset the clock for work within a building permit and certificate. Some construction contracts also require written notice or cure steps before suit. Those steps can run alongside the statute, so compare them against your contract. Under Section 95.11(6)(b), an action to enforce an equitable lien arising from the furnishing of labor, services, or material for the improvement of real property must be commenced within one year.

Why Discovery Dates and Tolling Can Change the Clock

The clock usually starts when a claim accrues, and only a few listed events pause it. Under § 95.031, accrual happens when the last element of the claim occurs.

Florida’s pause rules are narrow. Under § 95.051, a payment of part of the principal or interest on a written obligation pauses the clock. So does the pendency of an arbitral proceeding about the same dispute, which can matter when a business deal goes to arbitration.

Other listed reasons can also pause the clock, such as the defendant being out of state. Those rules in paragraphs (a)-(c), including the out-of-state rule, do not apply if process or service by publication can be made in a way that confers jurisdiction to grant the relief sought. The other listed reasons are not affected by this exception. A disability or other reason does not toll the running of a limitations period except for the categories specified in § 95.051, § 95.091, the Florida Probate Code, or the Florida Guardianship Law.

Common Mistakes That Shorten the Window

The most common mistake is assuming a long window applies without checking the claim type and start date. Several other errors cut the time even shorter.

First, waiting for settlement talks to end. Settlement talks are not among the tolling events listed in § 95.051, so they do not stop the calendar.

Second, assuming a later renewal or amendment restarts the clock. Renewals and amendments are not on that list either, so do not assume they reset the deadline.

Third, relying on a contract clause that sets a shorter filing period. Under § 95.03, that clause is void, but you may still lose time while the question is argued.

Fourth, relying on general summaries. Summaries give the general periods. They cannot account for your start date, your contract terms, or your recorded documents.

Have Questions About a Deadline in Your Property Dispute?

If you’re weighing a commercial property dispute now, the first step is naming the claim type and its start date. A tenant may have stopped paying rent on a space you own. A contractor may have recorded a lien on a building. A seller may have misstated facts before a closing.

Quick answers

How long do I have to sue over a written commercial lease in Florida?

Florida’s general period for a written contract is five years under Section 95.11.

Can a contract shorten the deadline?

No. A contract provision that sets a shorter filing period than the statute is void under Section 95.03.

Does arbitration pause the clock?

Under Section 95.051, the pendency of an arbitral proceeding about the dispute pauses the limitations period.

How long do I have to sue over a construction defect?

Generally four years, measured from a certificate or abandonment date, with a seven-year outer limit for construction claims.

Fees are discussed directly with you during any conversation with the firm. This page is the responsibility of Eduardo A. Maura at Ayala Law PA, whose office is at 1646 W Snow Ave, Tampa, Florida. The firm represents businesses in Tampa, Hillsborough County, and the Tampa Bay area. Some matters may be referred to another lawyer or firm where appropriate.

If a missed payment, a hidden defect, or an old handshake deal has you wondering whether your claim is still in time, reach out to Ayala Law PA at (305) 570-2208 or through the contact page so we can review your dates together.

Attorney advertising. The information on this page is for general informational purposes only and is not legal advice; reading it does not create an attorney-client relationship with Ayala Law PA. Prior results do not guarantee a similar outcome. Ayala Law PA, 1646 W Snow Ave, Tampa, FL 33606.

How our business litigation practice can help

Contract and lease review

We review the written agreement, lease terms and related records to identify the claims and defenses that may apply to your commercial property dispute.

Early attention to dates

We look at the dates that may matter to your matter early, so business owners can make informed decisions about next steps.

Business and entrepreneur focus

Our work centers on commercial and contract disputes, shareholder and partnership conflicts, construction litigation and real estate matters.

Florida courts and arbitration

We handle disputes in Florida courts and arbitration for businesses in Tampa, Hillsborough County and the wider Tampa Bay area.

Do not wait to get advice

Delay can affect your options in a commercial property dispute. Gather your lease, purchase or construction contracts, notices, payment records and correspondence now, and contact us before you send a demand or take other action.

Steps to take before you file

Collect your documents

Gather contracts, amendments, leases, notices, invoices, lien papers and emails related to the property or project.

Write a timeline

List key events, payments, breaches and communications with dates so the facts are clear from the start.

Note any dispute clauses

Check for arbitration, notice, mediation or venue provisions that may affect where and how a claim is brought.

Talk with counsel

Share your materials with our team so we can discuss the claims, defenses and practical options for your business.

Have a commercial property dispute? Contact Ayala Law PA to discuss your situation.

Related practice areas

Call Now (305) 570-2208