Change Order Not Paid? Construction Dispute Help in Tampa

Unpaid extra work can drain cash flow and stall a whole project. Here is how contractors and subcontractors in Tampa and Hillsborough County can start protecting their position.

By Eduardo A. Maura · Published November 20, 2026

If you did extra work and a change order is not paid, the dispute can move fast. Which path fits depends on your contract, your notices and your payment history.

This page explains how these disputes work in Florida and what to gather before you talk with a lawyer. Ayala Law PA’s only office is at 1646 W Snow Ave, Tampa, FL 33606, and the firm serves Tampa, Hillsborough County and the Tampa Bay area from that location.

What an unpaid change order means for a Tampa project

A change order is a written change to the scope, price or schedule of an existing construction contract. Owners and contractors use them when the work shifts after the contract is signed. Trouble usually starts when the extra work is done but not paid. The other side often argues one of three things:

  • The work was already in the base price.
  • The owner never approved the extra cost.
  • The change was never put in writing.

Many disputes come down to whether the work was truly extra. Your signed papers, your emails and the way the work was approved often matter a great deal.

Who this is for: general contractors, subcontractors, suppliers, developers and property owners in Tampa, Brandon, Riverview, Plant City, Temple Terrace and across Hillsborough County. Timing matters. Contract notice clauses and Florida lien law run on their own clocks, so waiting can cost you options.

If an unpaid change order is holding up your Tampa job, our team can review your contract and payment records with you and talk through your options. Talk it through with our team — we can walk you through how a situation like yours is usually handled and what your options are.

Construction site with cranes and steel framework silhouetted against a sunset sky.

What a construction change order dispute lawyer handles

A construction change order dispute lawyer handles claims for unpaid extra work, breach of contract, and the payment and lien issues that come with them. The firm focuses on business litigation, commercial litigation, contract disputes and construction litigation in Florida courts and arbitration.

Typical matters include:

  • Unpaid change order claims for approved or disputed extra work between a contractor, subcontractor and owner.
  • Breach of construction contract claims tied to changed scope, schedule or payment terms.
  • Back-charge disputes, where the other side deducts costs from what it says it owes you.
  • Construction lien enforcement, where Florida construction lien rights secure payment.
  • Real estate litigation tied to the project, including a recorded notice that affects the property.

Each claim turns on the contract’s exact words, so the review starts there. Not every claim fits every project. A lawyer can explain which claims your documents support.

Documents to gather before you contact a lawyer

Gather the contract and every change paper before you call. They set the terms of the dispute.

  • The original construction contract, with any change order, notice and attorney-fee clauses.
  • Every change order, proposal, pricing sheet and approval email, with dates, signed or not.
  • Daily logs, photos, timesheets, material invoices and delivery tickets showing the changed work.
  • Pay applications, invoices, signed lien waivers, and records of payments received and how they were applied.
  • Texts, emails and notices about the change, kept in original form.
  • A schedule showing when the change was requested, performed and accepted.

Keep originals. Don’t edit, delete or resend messages, even ones that seem unhelpful. If a document is missing, note that too. A missing approval is still a fact to explain.

How a change order dispute typically moves, step by step

A change order dispute usually moves through review, a written demand, and then negotiation, arbitration or a lawsuit. The order can vary, but these are the common steps:

  1. Review of the contract, change paperwork and payment history.
  2. A written demand or notice, following the contract’s notice steps.
  3. Negotiation or mediation, where the contract or the parties call for it.
  4. Lien steps, if Florida construction lien rights apply to the project.
  5. A lawsuit in Florida court or arbitration, if the contract requires it or the claim is not resolved.
  6. Discovery, motions, then trial or settlement.

Federal commercial cases filed in the Tampa Division follow the Middle District of Florida local rules. The timeline depends on the facts: the contract terms, the number of parties and whether liens are involved. For arbitration, the American Arbitration Association construction resources describe the procedures available to parties who agree to use them.

Lien and notice deadlines to act on now

Fla. Stat. § 713.08

Key points:

  • Serving the notice does not replace recording the claim of lien. Florida’s construction lien statute, Fla. Stat. § 713.22, sets a deadline for beginning an action to enforce a claim of lien, so the timing of a lien foreclosure matters.
  • Failure to pay undisputed amounts within 30 days after they are furnished and due, or within 30 days after payment is received, whichever last occurs, can entitle the unpaid provider to the complaint procedure and remedies in Fla. Stat. § 713.346.

Contract notice clauses need careful reading. Florida courts don’t favor treating a contract term as a step that must happen first. They do so only when plain language or necessary implication requires it. See Covelli Family v. ABG5.

Why work with Ayala Law PA on a Tampa construction dispute

Ayala Law PA is a business litigation firm in Tampa, with its only office at 1646 W Snow Ave, Tampa, FL 33606.

The firm focuses on business litigation, commercial litigation, contract disputes, shareholder disputes, construction litigation, real estate litigation and international trade litigation.

Eduardo A. Maura is the responsible lawyer for this page. The firm’s lawyers handle matters in Florida courts and arbitration. Clients in Hillsborough County and the Tampa Bay area are served from the Tampa office.

Bring the documents listed above to your first conversation, so the review can start with the facts.

Not sure what your next step is?

Talk it through with our team — we can walk you through how a situation like yours is usually handled and what your options are.

Glass office building under construction with a tall crane against a clear blue sky.

Frequently asked questions about unpaid change orders

Do I need a signed change order to get paid?

A signed change order helps. Emails, the contract and how the work was handled can also matter.

Can I stop work if a change order is not paid?

Whether you can stop depends on your contract’s terms and notice requirements. Check those before you act.

Can I file a lien for unpaid change order work?

Lien rights depend on the project, the parties and the notice steps. Some changed work may support a lien, and other work may not.

Can I recover attorney fees?

Sometimes. If a contract lets a party recover fees for enforcing it, Fla. Stat. § 57.105 lets a court allow fees to the other party when that party prevails, but only for contracts entered into on or after October 1, 1988.

If an unpaid change order is holding up a live job in Tampa, bring your contract and payment records to a conversation with Ayala Law PA. Call (813) 414-5715 or send your details through the contact form.

Attorney advertising. The information on this page is for general informational purposes only and is not legal advice; reading it does not create an attorney-client relationship with Ayala Law PA. Prior results do not guarantee a similar outcome. Ayala Law PA, 1646 W Snow Ave, Tampa, FL 33606.

How Ayala Law PA Approaches Construction Payment Disputes

Contract and change order review

We read the contract, its notice provisions and any change order language to see how the disputed work was documented and approved.

Communication history

Emails, text messages, meeting notes and daily logs often show what was requested, who approved it and what was agreed.

Practical options

We discuss the options available for your situation, from demand letters and negotiation to lien rights and litigation in Florida courts.

Protecting your business

Our team focuses on keeping your cash flow, bonding and ongoing project relationships in view while your claim moves forward.

Check Your Contract Before You Stop Work

Walking off a job or filing a lien without reviewing your contract's notice requirements can affect your position. Gather your documents first and talk with a lawyer before taking action.

What to Gather Before You Call

Signed and unsigned change orders

Keep every written request, approval, rejection and revised scope, even if the paperwork was never finalized.

Emails and messages

Save the full threads with the owner, general contractor or project manager, including dates and attachments.

Invoices and payment records

Bring pay applications, invoices sent, payments received and any retainage or withholding notices.

Field records

Daily logs, photos, timesheets, material receipts and inspection reports help show what extra work was performed.