You did the work, sent the invoices, and the payments stopped. A payment bond is a surety’s promise to pay subcontractors, laborers, and suppliers when the contractor does not, and it may be a route to getting paid. Whether it works for you depends on the project type, the bond terms, and whether you meet the notice and deadline steps.
This page explains what a payment bond covers, the deadlines that control a claim, and the steps that usually follow when payment stops.
What a Payment Bond Is and Who Can Make a Claim
A payment bond protects the people who furnish labor, services, or materials to a bonded project. On public work, a contractor on a formal contract must record a payment and performance bond in the county public records before starting. The surety must be authorized to do business in Florida, under Fla. Stat. § 255.05.
On private projects, a payment bond is not mandatory on every job: under § 713.23(1)(a), it is the bond required to exempt an owner under Florida’s Construction Lien Law, and when it is used for that purpose the contractor must post it in at least the amount of the original contract price before work on the improvement starts. A copy must be attached to the recorded notice of commencement, under Fla. Stat. § 713.23.
A performance bond is different. It protects the owner if the contractor fails to finish the work. Many bonded jobs carry both. Whether you qualify depends on the facts of your work, your place in the supply chain, and the bond’s terms.
If unpaid invoices have stalled your bonded job, you may have a claim that needs review soon, and our team can talk it through with you. Talk it through with our team — we can walk you through how a situation like yours is usually handled and what your options are.

What a Payment Bond Covers
A payment bond generally covers unpaid amounts for labor, services, and materials you furnished to the bonded project. Under the public-bond statute, your claim can include the amount due and unpaid finance charges under your contract (Fla. Stat. § 255.05).
Attorney’s fees are possible but not automatic. In an action to enforce a claim against a bond under Part I of Chapter 713, the prevailing party is entitled to a reasonable fee the court sets (Fla. Stat. § 713.29). Who prevails depends on how the case ends.
A bond does not pay for amounts unrelated to your work on the project. Disputes over the contract price can also limit fast remedies, which we cover below.
Deadlines That Control Your Claim
The clock usually starts on your last day of work or delivery. It does not start on the day an invoice went unpaid.
Under Fla. Stat. § 95.031, a cause of action accrues when its last element occurs. For a claim to enforce a payment bond, Fla. Stat. § 95.11 sets a one-year period under paragraph (6)(e) for claims on bonds where the principal is a contractor, subcontractor, or sub-subcontractor, covering private work as well as public work, except for actions governed by s. 255.05(10), s. 337.18(1), or s. 713.23(1)(e). It runs from your last furnishing of labor, services, or materials, or from the contractor’s last furnishing if that is later.
On private work, a notice of nonpayment is a condition of recovery. It must be under oath.
Public-project notice and suit steps are set separately in the public-bond statute. Find out early which set of rules applies to your job.
Count days carefully. For time periods under Part I of Chapter 713, a deadline that lands on a weekend or holiday moves to the next business day (Fla. Stat. § 713.011). Notices under that part must be in writing (Fla. Stat. § 713.012).
Step-by-Step: How a Payment Bond Claim Works
A payment bond claim usually follows six steps. Most of them start with your paperwork.
- Gather your records. Pull the contract, purchase orders, delivery tickets, daily logs, change orders, invoices, and payment history.
- Get a copy of the bond. On public work, a claimant may apply to the governmental entity in charge of the work for the contract and the recorded bond (Fla. Stat. § 255.05).
- Serve written notice on the contractor and surety within the time the statute requires.
- File suit if the claim stays unpaid. Under Fla. Stat. § 47.011, actions must be brought in the county where the defendant resides, where the cause of action accrued, or where the property in litigation is located, but this rule does not apply to actions against nonresidents. Circuit court cases follow the Florida Rules of Civil Procedure.
- Expect the case to move at its own pace. Timelines vary with the amount, the defenses raised, and court schedules.
Common Defenses and Problems Sureties and Contractors Raise
Most bond claims get challenged on notice, timing, or the amount owed. Expect these arguments early.
- Notice problems. A minor mistake in a notice of nonpayment does not defeat an otherwise valid claim. A notice of nonpayment must include a declaration that its facts are true to the best of the signer’s knowledge and belief (Fla. Stat. § 713.23).
- Disputed amounts. Under Fla. Stat. § 713.346, the fast remedies do not apply to the extent of a bona fide dispute over the contract price.
- Waivers. A waiver signed for a progress payment does not cover retention or work done after the date it names (Fla. Stat. § 713.235). Check the date and scope before you sign.
- Pay-if-paid terms. Some contracts tie your payment to the owner paying the contractor. Those terms can change when money is due, so read the wording early.
Why Ayala Law PA for Hillsborough County Bond Claims
Ayala Law PA focuses its practice on business litigation, construction litigation, and contract disputes in Florida courts and arbitration. Its construction work includes contractor and subcontractor disputes and lien foreclosure matters.
The firm’s only office is at 1646 W Snow Ave, Tampa, FL 33606. It serves Hillsborough County and the Tampa Bay area from that Tampa office.
Eduardo A. Maura is the responsible lawyer for this page. Our team, including support staff, handles intake, document organization, and case preparation.
In practice, the work starts with the bond and the contract, a list of deadlines, and written communication with the contractor and surety.
Not sure what your next step is?
Talk it through with our team — we can walk you through how a situation like yours is usually handled and what your options are.
Frequently Asked Questions
Can a subcontractor make a payment bond claim if the prime contractor went out of business?
The bond may still be a source of recovery, because the statute gives claimants a cause of action against the contractor and surety. The deadlines still apply, so act quickly.
Do I need a lawyer to send a notice of nonpayment?
The notice rules are technical, and a missed step can cost you the claim. A lawyer can check the form, timing, and recipients for your project.
Is a payment bond the same as a lien?
No. A lien attaches to the property, while a bond is the surety’s promise to pay. The terms of each contract and the specific facts of a dispute can affect which options are available.
What if the owner already paid the contractor?
An owner’s payment does not automatically pay your balance. The bond terms and the statutes control what you can recover.
How long does a payment bond claim take?
Timelines vary with the amount, the defenses raised, and the court’s schedule. No single timeline fits every case.

Talk to Our Team About Your Bonded Project
If you are waiting on money for work already done, you may have a claim that needs review soon. That may mean a subcontractor with invoices unpaid for weeks, a supplier waiting on a final draw, or a family member helping a small contracting business through a stalled job.
Reach out to Ayala Law PA at (813) 414-5715, or send a case evaluation request at lawayala.com/contact. We can talk through the bond, the deadlines, and the records you have.